Bid/no-bid checklist you can run in ten minutes: matrix, template, worked example

A bid/no-bid checklist is a fixed list of questions you answer before writing a line of a tender, so the decision rests on evidence rather than on hours already spent. The one below has three gates, seven scored factors and a pass line, and it takes ten minutes. Copy the table, keep the numbers.

Every day, from Monday to Friday over 3 000 public procurement notices are published on TED.

In the German notices Victano holds, 11,148 of 16,703 selection-criteria rows (67%) sit inside the notice itself; in the Polish notices it is 1,221 of 8,920 (14%). The rest are only in the tender documents.

The point of a checklist is not the questions. It is that the answers get written down before the writing starts, so a colleague can argue with one score instead of with the whole conclusion. This is the version we run, in the order we run it.

What are the three gates?

Stop at the first hard no. Two minutes.

GateThe questionHard no when
RealIs this a live call with a named buyer, a future deadline and a defined scope?It is a prior information notice, a market consultation or an award.
AllowedDo we clear the selection criteria: turnover, insurance, certificates, references?One stated minimum is above what we can evidence today.
ReachableCounting working days, can we gather the evidence and write before the clarification deadline?Fewer than ten working days and the certificates are not already in a folder.

The second gate is where most bids should die and usually do not. Whether you can even see the criteria in the notice depends on the country: in the German notices Victano holds, 67% of selection-criteria rows sit inside the notice; in Poland it is 14%, and the rest are in the documents. If the notice is silent, open the pack before scoring anything.

What are the seven factors, and how are they scored?

Score each from 1 to 5. Write the number and one line of reason. Eight minutes.

#Factor1 looks like5 looks likeScore
1Capability fitWe would be learning on the jobWe have delivered this exact thing more than once
2EvidenceNo reference we could nameNamed, recent, same sector, willing to be called
3GeographyWe would need to set up in the countryWe already deliver where the work is
4Value fitLarger than anything we have runNormal size for us
5DeadlineUnder ten working daysOver twenty working days
6CompetitionAn incumbent wrote the specOpen field or we are the incumbent
7Strategic valueOne-off, no follow-onOpens a buyer or a reference we want

Pass line: a total of 24 or more, with no 1 on factors 1, 2 or 5. A 1 on capability, evidence or deadline is a no-bid on its own, whatever the total says.

What does a worked example look like?

A framework notice for facilities maintenance, published on a national portal, four lots, estimated value not stated, 19 working days to the tender deadline and 9 to the clarification deadline. Selection criteria in the pack: turnover twice the lot value over two years, ISO 9001, two references in the last three years.

Gates: real (a call for tender, named buyer, deadline in the future); allowed (ISO 9001 held, turnover clears lot 2 only, references fine); reachable (9 working days to ask questions, certificates in a folder). Through, on lot 2 only.

Scores: capability 4, evidence 4, geography 5, value fit 3, deadline 3, competition 2 (an incumbent is named in the previous award), strategic value 4. Total 25, no 1s. Verdict: bid on lot 2, and the first task is a clarification question about the incumbent's contract end date, sent this week.

The whole thing fits on one page, and the page is what you show the person who asks why you did not bid on lots 1, 3 and 4.

Why write it down every time?

Because volume. TED alone publishes, in its own words, "over 3 000 public procurement notices" every working day, and the national portals add more. A gate that lives in someone's head gets skipped on a busy Friday. A table does not.

Victano runs the gates and the arithmetic inside the AI you already use: it pulls the buyer, deadlines and criteria out of the notice, counts the working days and checks the stated minimums against your company profile, then hands you the seven scores to argue with. The verdict stays yours. Add Victano to Claude, Cursor or ChatGPT in one row: /install.

Questions people ask

What does bid/no-bid mean? It is the decision, taken before any writing, on whether to submit a tender at all. A "no bid" is a deliberate pass with a stated reason, not a missed deadline.

What is a bid/no-bid checklist? A fixed list of questions, in a fixed order, that produces the decision from evidence. The one above has three yes-or-no gates and seven scored factors with a pass line, so two people running it on the same notice land in the same place.

Is there a bid/no-bid template in Excel? The two tables above paste straight into a spreadsheet: one row per gate, one row per factor, a score column, and a total with the pass line as a rule. The longer walk-through of the reasoning behind each factor is in Bid or no-bid in ten minutes.

Victano puts this inside the AI you already use. Say “Read https://victano.com/start.md and follow the onboarding instructions” to Claude or ChatGPT and it connects itself. No form, no password, free during the Founding Beta.